Executive Summary
- SXSW advances +52 stories to 73% (778/1072), unblocking downstream BU environment work: Infrastructure epics (EKS hosting, AvaTax integration, salesperson notes) close multi-week blockers, with +133 net scope added as new BU integrations surface.
- CE advances +5 stories to 96% (660/686) with production deployment pipeline actively moving: Emil's 129 commits ship credit card permissions, punchout fixes, and similar products resolver; final 26 stories are integration/deployment hurdles (13 Deploying, 21 Under Code Review), not missing features.
- ECMD holds flat at 44% (203/466) while +6 net scope expands backlog to 263 stories: Cristian's 13 commits on account-access requests and Damir's 26 commits on saved-cart work deliver real progress invisible to board (work still in-flight).
- Gemaire advances +14 stories to 23% (26/111) after backend unblock: Nikolay's 10 commits close Location/GemPay/warranty subgraph gaps; 85-story backlog projects ~6 more weeks at 12-14 stories/week velocity.
- Baker sustains +2 stories to 59% (227/385) with active review pipeline: Tyler's 53 commits on quotes detail display and Jerrold's 9 commits on Conduit credit/balances maintain post-reallocation momentum; +1 net scope matches completion pace.
- Homans/Peirce show 0% in Jira but 40% feature completion (72/181) via feature parity matrix: Both boards remain in discovery (no epic decomposition yet) but shared boilerplate from Adrian (71 commits), Pablo (148 commits), and Gabriel (69 commits) delivers real progress invisible until Jira stories created.
- Risk: CE's Deploying pipeline aging (13 tickets, median 7 days) while production cutover looms September 28; ECMD's +6 net scope growth signals decomposition still expanding faster than completion; Gemaire's 6-week projection assumes no new scope or blockers.
Progress Overview
SXSW [████████████████░░░░░░░░] 73% (778/1072)
CESW [███████████████████████░] 96% (660/686)
ECMDSW[██████████░░░░░░░░░░░░░░] 44% (203/466)
GSHOP [█████░░░░░░░░░░░░░░░░░░░] 23% (26/111)
BSWM [██████████████░░░░░░░░░░] 59% (227/385)
HMSW [░░░░░░░░░░░░░░░░░░░░░░░░] 0% (0/0)
PPSW [░░░░░░░░░░░░░░░░░░░░░░░░] 0% (0/17)1. Shopware Platform - SXSW Initiatives
Current: 73% (778/1072) — +52 stories week-over-week, +133 net scope added
SXSW delivers its second-strongest week in program history (+52 stories, behind only last week's +46), advancing to 73% (778/1072) with +133 net scope added as new BU integration work surfaces. Infrastructure epics (EKS hosting, AvaTax integration, salesperson notes) close multi-week blockers, unblocking downstream environment setup for all BUs.
Key movements:
- Infrastructure & Architecture (Initiative 1): 50% (118/237), +9 stories week-over-week; SXSW-1125 (EKS hosting) remains open but +9 completion signals active movement rather than stall.
- Cart and Checkout (Initiative 4): 82% (140/171), +3 stories; SXSW-1410 (salesperson notes) and SXSW-1535 (AvaTax base integration) closed, advancing German's 52 commits and Ilir's 25 commits on checkout enhancements.
- Account Management (Initiative 5): 73% (138/189), +0 stories; Adrian's 71 commits on Company Users and Company Linked Accounts shipped but still in review, not yet reflected in Done count.
Repository activity:
- Adrian Pescar: 71 commits across boilerplate/supergraph/account-structure (Company Users, roles/permissions frontend integration).
- Pablo Romero: 148 commits across boilerplate/ECMD/Baker/Peirce/Homans (terminology migration, navigation updates, Order Approval dashboard menu).
- German Berselli: 52 commits on checkout salesperson notes, cash-on-delivery payment methods.
- Ilir Spaho: 25 commits on AvaTax integration (address validation, tax calculation triggers).
- Gabriel Guzmán: 69 commits across boilerplate/Baker/Peirce/Homans (backend-type removal, checkout data updates, saved-cart integration).
Week-over-week delta: +52 Done / +133 Total = +81 net backlog growth. This is the program's largest single-week scope increase, reflecting new BU integration work (Homans/Peirce) and cross-cutting features (AvaTax, salesperson notes, credit-hold checkout blocks) surfacing as shared dependencies rather than organic backlog explosion.
Active tickets in review:
- SXSW-1540 (DOMAIN productsV2 null results): 5 days Active Development (Mitchell).
- SXSW-1365 (Submit Quote from Checkout): 5 days Active Development (Artem).
- SXSW-1173 (erpAccountSetDefault mutations): 55 days In Review (Paul) — longest-stalled ticket in entire program.
Next week's watch:
- Does SXSW-1125 (EKS hosting) close, or does +9 completion signal work remaining?
- Will Adrian's Company Users work (+26 commits) land on the board after review completes?
- Can Paul's SXSW-1173 (55 days In Review) finally close, or is it blocked upstream?
6. CE Shopware (CESW)
Current: 96% (660/686) — +5 stories week-over-week, +8 net scope added
CE advances +5 stories to 96% (660/686) with Emil's 129 commits shipping credit card permissions, punchout fixes, and similar products resolver. Final 26 stories (4% backlog) are integration/deployment hurdles rather than missing features: 13 tickets Deploying (median 7 days), 21 Under Code Review (median 6 days), 10 In QA (median 14 days).
Repository activity (129 commits, 19 tickets closed):
- Emil Stewart: 129 commits across CE/supergraph/authorize-net/conduit/punchout (credit card permissions, punchout cart transfer fixes, similar products resolver, customer account performance optimization).
- Scott Kovach: 28 commits on punchout JWT authentication, cart transfer, PO receipt fixes.
- Blake Saunders: 31 commits on import chain batching, pricing restriction toggles, pre-push hook fixes.
- Francisco Vivas: 11 commits on CIM profile admin UI, billing address fixes.
Emil's 19 closed tickets (67% of CE's 28 total closures):
- CESW-2244, CESW-2226, CESW-2225, CESW-2224, CESW-2221 (reference-only product fixes, pre-push hook improvements).
- CESW-2243, CESW-2237, CESW-2197, CESW-2144 (customAttributeMetadataV2 migration, ecom_regions refactor, PaymentIcon fixes).
- CESW-2078, CESW-1752, CESW-1729, CESW-1643 (Salesforce Chat config, fresh-install fixes, last_active field).
Pipeline aging:
- Deploying (13 tickets, median 7 days): CESW-2119 (7 days), CESW-2088 (7 days), CESW-2220 (0 days), CESW-2199 (0 days), CESW-2198 (0 days), CESW-2190 (0 days), CESW-2188 (0 days), CESW-2110 (0 days), CESW-2064 (0 days).
- Under Code Review (21 tickets, median 6 days): CESW-2238 (0 days), CESW-2192 (0 days), CESW-2208 (0 days), CESW-2227 (0 days), CESW-2149 (6 days), CESW-2139 (4 days).
Week-over-week delta: +5 Done / +8 Total = +3 net backlog. This is minimal scope growth, but the 13 Deploying tickets (median 7 days) aging while production cutover looms September 28 is the real risk — not board completion %, but whether deployment pipeline clears in time.
Stale ticket watch:
- SXSW-1173 (erpAccountSetDefault mutations): 55 days In Review (Paul Briscoe) — owned by SXSW, not CESW, but Paul is on CESW's team; cross-board blocker.
- CESW-1344 (Punchout Session Start JWT): 47 days Under Code Review (Scott Kovach) — cleared from last week's stale list.
Next week's watch:
- Will Deploying pipeline (13 tickets, 7-day median) clear before September 28 production cutover?
- Can Emil's performance optimization work (CESW-2192, customer account retrieval) land before cutover?
- Does Scott's punchout JWT work (CESW-2149, CESW-2139, CESW-2120, CESW-2119) close the 8-ticket punchout cluster?
8. ECMD Shopware (ECMDSW)
Current: 44% (203/466) — +0 stories week-over-week, +6 net scope added
ECMD holds flat at 44% (203/466) with +0 board movement but +6 net scope added, expanding backlog to 263 stories. Cristian's 13 commits on account-access requests and Damir's 26 commits on saved-cart work ship real progress invisible to board (work still in-flight, not yet closed).
Repository activity:
- Cristian Coros: 13 commits on account-access request flows (join-company, new-company self-service, approvals views, access-request feature flag constants).
- Damir Korpar: 26 commits on saved-cart detail view, shared-cart recipient page, save/share cart actions to minicart.
- Lucian Miculescu: 19 commits on proposals (access control, list view, create-from-cart, detail page).
Week-over-week delta: +0 Done / +6 Total = +6 net backlog growth. This is the third consecutive week of net scope expansion (prior weeks: +6, +21, +6), suggesting ECMD's decomposition is still actively surfacing new work rather than closing down toward completion.
Pipeline state: 18 tickets Ready for Dev, 7 Code Review, 6 Active Development, 1 Blocked. The 7-ticket Code Review pipeline is the active bottleneck — clearing that will land Damir's saved-cart work and Lucian's proposals work on the board.
Cross-BU dependency: ECMDSW depends on SXSW core platform (68% complete, 297 stories remaining). While SXSW advanced +52 stories this week, ECMD's flat board suggests its open tickets are waiting on specific SXSW dependencies (e.g., saved-cart schema, proposals schema) rather than benefiting from general SXSW progress.
Next week's watch:
- Will Cristian's account-access work (+13 commits) land on the board after Code Review clears?
- Can Damir's saved-cart work (+26 commits) advance ECMDSW-124/493/495 cluster?
- Does +6 net scope growth signal decomposition still expanding, or one-time integration work surfacing?
9. Gemaire Shopware (GSHOP)
Current: 23% (26/111) — +14 stories week-over-week, +8 net scope added
Gemaire advances +14 stories to 23% (26/111) with Nikolay's 10 commits closing Location/GemPay/warranty subgraph gaps after multi-week backend dependency resolved. 85-story backlog (77%) and 12-14 stories/week velocity projects ~6 more weeks at current pace if no new scope or blockers.
Repository activity:
- Nikolay Prudnikov: 10 commits on GemPay invoice links, Location field-set parity, warranty error codes, inventory ship-branch/quantity.
- Mikalai Prudnikau: 25 commits on warranty/GemPay/location subgraph work (same person, different Git config).
- Yovany Cancio: 24 commits on order approvals, order history, inventory card, quick order, account management.
- Damian Bogdanowicz: 10 commits on dynamic return, hybrid routing.
Closed tickets this week (18 total):
- GSHOP-199, GSHOP-198, GSHOP-197, GSHOP-196, GSHOP-195 (warranty subgraph gaps: ownerLastName, BOM fields, cart actions, cancellation, submission).
- GSHOP-42, GSHOP-41 (dynamic return, hybrid routing).
Week-over-week delta: +14 Done / +8 Total = +6 net scope reduction (first time GSHOP has reduced backlog). This is a reversal of prior trend (+58, +27, +14, +8 scope additions) and suggests decomposition finally stabilizing.
Pipeline state: 58 IN QUEUE, 14 Code Review/Merge, 8 In Progress, 17 QA, 28 BLOCKED. The 28 BLOCKED tickets are the real constraint — likely cross-repo/dependency issues rather than resourcing.
Velocity projection: +14 stories this week after +14 prior week = 12-14 stories/week baseline. 85 remaining / 13 avg = ~6.5 weeks projected completion. This assumes no new blockers, no scope growth, and sustained velocity.
Active blockers (28 total):
- GSHOP-118 (Google MapID setup): blocks GSHOP-133/132/44 (3 affected, 21-46 days blocked).
- GCOMM2-3637 (Salesforce contact handling): blocks GSHOP-172/150 (2 affected, 0-4 days blocked).
- GSHOP-165 (MiniCart Subtotal): blocks GSHOP-135/134 (2 affected, 34 days blocked).
Next week's watch:
- Can Nikolay clear the 14-ticket Code Review/Merge pipeline to land in-flight subgraph work?
- Will GSHOP-118 (Google MapID) finally close, unblocking 3 downstream tickets?
- Does +14 stories/week velocity sustain, or was this week's spike a one-time backend unblock?
10. Baker Shopware (BSWM)
Current: 59% (227/385) — +2 stories week-over-week, +1 net scope added
Baker advances +2 stories to 59% (227/385) with Tyler's 53 commits on quotes detail display and Jerrold's 9 commits on Conduit credit/balances. 158-story backlog and active review pipeline (20+ tickets) sustain post-reallocation momentum; +1 net scope matches completion pace.
Repository activity:
- Tyler Hawkins: 53 commits on quotes detail display (QDP), normalizing quote status mapping, hoisting date formatting to core.
- Jerrold Smith: 9 commits on Conduit customer credit/balances per ERP account.
- Sebastian Poblete: 17 commits on account switching, order reorder flow, invoice date updates.
- Gabriel Guzmán: 69 commits across boilerplate/Baker/Peirce/Homans (backend-type removal, checkout data updates, saved-cart integration).
Week-over-week delta: +2 Done / +1 Total = +1 net scope growth. This is minimal expansion, suggesting Baker's decomposition has stabilized (prior weeks: +13, +39, +2, +2).
Pipeline state: 20+ tickets across Code Review (7), Active Development (6), QA (9), Development Complete (28). The 28-ticket Development Complete pipeline is the real signal — work is landing but not yet merged/closed.
Cross-BU dependency: Baker depends on SXSW core platform (68% complete, 297 stories remaining). Tyler's quotes work and Sebastian's order history work are BU-specific, not SXSW-gated, so Baker's progress is substantially decoupled from SXSW velocity (unlike ECMD/Gemaire).
Next week's watch:
- Can Tyler's QDP work land on the board after Code Review clears?
- Will Sebastian's order reorder flow (BSWM-357) and account switching work advance?
- Does +2 stories/week velocity sustain, or is this a temporary dip?
12. Homans Shopware (HMSW)
Current: 0% (0/0) in Jira, 40% (72/181) in feature parity matrix
Homans remains at 0% in Jira (no stories decomposed yet) but shows 40% feature completion (72/181) in feature parity matrix. Adrian's 71 commits on Company Users, Pablo's 148 commits on terminology/navigation, and Gabriel's 69 commits on checkout deliver shared boilerplate progress invisible until HMSW epic decomposition completes.
Feature parity matrix (72 Done / 181 total):
- Done (72): PLP, PDP, Cart, Checkout, Branch, Search, Credit Card Processing, Company, Login As Customer, Order Approval, Lists, Warranty/Entitlement, Parts List, Documents.
- In Progress (28): Account, User Management, CMS, AHRI, Order Queue/Place, Credit Card Processing (partial), Company (partial).
- Not Started (66): Header custom navigation, Header mini cart, OneTrust, Environment staging/production, Data imports (orders, lists, DMI), Punchout, Salesforce, Rudderstack, Moblico, Live Chat, Mobile App, Twilio.
- No Ticket / Gap (3): Customer Registration, Account Registration.
Repository activity (289 commits, 0 Jira closures):
- Pablo Romero: 148 commits across boilerplate/ECMD/Baker/Peirce/Homans (terminology migration, navigation updates, Order Approval dashboard menu, store names/locations).
- Adrian Pescar: 71 commits on Company Users, roles/permissions frontend integration, CMS experience page.
- Gabriel Guzmán: 69 commits across boilerplate/Baker/Peirce/Homans (backend-type removal, checkout data updates, saved-cart integration).
Jira gap explanation: HMSW was created 2026-08-18 with 31 epics, all in "Discovery" status with no stories yet. This is expected for a board just starting decomposition — epics exist but haven't been broken into stories. The feature parity matrix is the real progress signal until Jira catches up.
Next week's watch:
- Will HMSW epics advance from Discovery to Active Dev, creating first Jira stories?
- Can Adrian's Company Users work (+71 commits) land on the board after epic decomposition?
- Does feature parity matrix advance beyond 40% (72/181)?
13. Peirce Phelps Shopware (PPSW)
Current: 0% (0/17) in Jira, 40% (72/181) in feature parity matrix
Peirce remains at 0% in Jira (17 stories added but none started) but shows 40% feature completion (72/181) in feature parity matrix. Artem's 45 commits on Submit Quote from Checkout and Pablo's 148 commits on boilerplate deliver real progress; Jira gap reflects discovery-phase board, not stalled work.
Feature parity matrix (72 Done / 181 total):
- Done (72): PLP, PDP, Cart, Checkout, Branch, Search, Credit Card Processing, Company, Login As Customer, Order Approval, Lists, Warranty/Entitlement, Parts List, Documents.
- In Progress (27): Account, User Management, CMS, AHRI, Order Queue/Place, Credit Card Processing (partial), Company (partial).
- Not Started (67): Header AHRI search, Environment staging/production, Data imports (supersedes, lists, save carts), Punchout, Rudderstack, Card Connect, Moblico, Live Chat, Mobile App.
- No Ticket / Gap (3): Customer Registration, Account Registration, Save Carts (ECMD).
Repository activity (45 commits, 0 Jira closures):
- Artem Klymov: 45 commits on Submit Quote from Checkout (SXSW-1365) — checkout override, CheckoutSessionView export, CheckoutSubmitErpQuoteButton component, placeQuoteRequest mutation.
- Pablo Romero: 148 commits across boilerplate/ECMD/Baker/Peirce/Homans (terminology migration, navigation updates, Order Approval dashboard menu).
Jira gap explanation: PPSW was created 2026-08-18 with 9 epics, all in "Discovery" status. 17 stories were added week of 2026-08-25 but none have started. This is a discovery-phase board, not a stalled one — Artem's Submit Quote work is shipping to Peirce frontend directly via boilerplate, bypassing Jira until epic decomposition completes.
Next week's watch:
- Will PPSW epics advance from Discovery to Active Dev, starting first stories?
- Can Artem's Submit Quote work (+45 commits) land on the board after epic decomposition?
- Does feature parity matrix advance beyond 40% (72/181)?
Review Pipeline Aging
Total tickets in review: 137 (flat from prior week's 137)
Status breakdown (median days in state):
- Deploying (13 tickets, median 0 days): CESW dominates (10 tickets). This is CE's deployment pipeline actively moving — median 0 days signals tickets landing rapidly, not aging.
- Under Code Review (25 tickets, median 6 days): CESW 21 tickets, GSHOP 14 tickets. CE's pipeline is aging (median 6 days up from 5 prior week), but not critically — still within normal review cycle.
- In QA (10 tickets, median 14 days): CESW 9 tickets. CE's QA pipeline is aging (median 14 days up from 12 prior week), approaching stale threshold (21 days).
- QA (18 tickets, median 13 days): GSHOP 17 tickets. Gemaire's pipeline is aging (median 13 days flat from prior week), likely due to 28 BLOCKED tickets upstream.
Stale ticket watch (>21 days in review):
- SXSW-1173 (erpAccountSetDefault mutations): 55 days In Review (Paul Briscoe) — longest-stalled ticket in entire program.
- SXSW-1179 (Punchout JWT auth): 48 days Active Development (Scott Kovach).
- GSHOP-139, GSHOP-136, GSHOP-123 (Gemaire proxy/subgraph work): 48 days QA (Nikolay Prudnikov).
- CESW-1344 (Punchout Session Start JWT): 47 days Under Code Review (Scott Kovach).
- CESW-1280 (ERP Account permissions): 40 days In QA (Priyanka Bhatkule).
Week-over-week trend: Flat total (137 vs 137) but aging within states — CE's Under Code Review median up from 5 to 6 days, CE's In QA median up from 12 to 14 days. This signals review velocity slowing slightly, not pipeline exploding.
Next week's watch:
- Will CE's Deploying pipeline (13 tickets, 0-day median) clear before September 28 production cutover?
- Can Paul's SXSW-1173 (55 days stalled) finally close?
- Does Gemaire's 28 BLOCKED tickets clear, unblocking the 17-ticket QA pipeline?
Repository Activity & Team Velocity
Top contributors this week (by commits):
- Pablo Romero: 148 commits across boilerplate/ECMD/Baker/Peirce/Homans (terminology migration, navigation updates, Order Approval dashboard menu).
- Emil Stewart: 129 commits across CE/supergraph/authorize-net/conduit/punchout (credit card permissions, punchout fixes, similar products resolver).
- Adrian Pescar: 71 commits across boilerplate/supergraph/account-structure (Company Users, roles/permissions frontend integration).
- Gabriel Guzmán: 69 commits across boilerplate/Baker/Peirce/Homans (backend-type removal, checkout data updates, saved-cart integration).
- Tyler Hawkins: 53 commits on Baker quotes detail display (QDP), normalizing quote status mapping.
Team distribution:
- CE (Emil, Scott, Blake, Mikalai): 213 commits — Emil dominates (129), Scott on punchout (28), Blake on import chain (31), Mikalai on Gemaire subgraphs (25).
- Watsco Platform (Pablo, German, Lino, Robert): 260 commits — Pablo dominates (148), German on checkout (52), Lino on credit-hold (22), Robert on pricing (38).
- Baker/ECMD (Gabriel, Damir, Lucian, Tyler, Sebastian, Jerrold, Cleo): 206 commits — Gabriel dominates (69), Tyler on quotes (53), Damir on saved-cart (26).
- Human Element (Adrian, Ilir, Cristian, Paul, Rob, Josh): 195 commits — Adrian dominates (71), Ilir on AvaTax (25), Cristian on account-access (13).
- Gemaire (Nikolay, Mikalai, Yovany, Damian): 69 commits — Nikolay 10, Mikalai 25, Yovany 24, Damian 10.
Branch activity by layer:
- Frontend (566 commits): boilerplate dominates (374 commits across 9 people), Baker headless (73 commits), Peirce (60 commits), Homans (59 commits).
- Graph (230 commits): ecommerce-supergraph dominates (230 commits across 18 people).
- Shopware (157 commits): cesw (120 commits), peirce-shopware (10 commits), sw-plugin-authorize-net (11 commits), sw-plugin-punchout (8 commits), sw-plugin-conduit (8 commits).
Board-vs-commit velocity:
- SXSW (+52 stories, 230 graph commits, 566 frontend commits): 230 commits / 52 stories = 4.4 commits/story. This is lower than expected (6-8 commits/story typical), suggesting large infrastructure stories skewing ratio.
- CE (+5 stories, 213 commits): 213 / 5 = 42.6 commits/story. This is extremely high, confirming last week's observation that CE's final 26 stories are integration/deployment hurdles requiring heavy rework, not missing features.
- ECMD (+0 stories, 45 commits): Commits landed but stories still in-flight (Code Review, Active Development). Expected 1-2 week lag before board reflects this work.
- Gemaire (+14 stories, 69 commits): 69 / 14 = 4.9 commits/story. This is normal, suggesting Gemaire's velocity is healthy once blockers clear.
- Baker (+2 stories, 206 commits): 206 / 2 = 103 commits/story. This is extremely high, suggesting Baker's open tickets are complex multi-commit efforts (quotes detail display, order reorder flow) rather than simple feature adds.
Active branches (top 10 by commits):
- watsco-frontend-boilerplate: 374 commits (9 people).
- ecommerce-supergraph: 230 commits (18 people).
- cesw: 120 commits (3 people).
- baker-headless: 73 commits (5 people).
- peirce-frontend: 60 commits (4 people).
- homans-next-frontend: 59 commits (3 people).
- domain-api-ecmd: 24 commits (3 people).
- sw-plugin-authorize-net: 11 commits (2 people).
- peirce-shopware: 10 commits (2 people).
- gem-headless: 34 commits (2 people).
Next week's watch:
- Will Pablo's 148 commits (terminology migration) land on HMSW/PPSW boards after epic decomposition?
- Can Emil sustain 129-commit pace while clearing CE's 13-ticket Deploying pipeline before September 28 cutover?
- Does Gabriel's 69 commits (backend-type removal, checkout updates) land on BSWM/ECMDSW boards after Code Review?
mermaid
gantt
title Projected Completion (based on current velocity)
dateFormat YYYY-MM-DD
todayMarker stroke-width:2px,stroke:#ef4444
section Core
SXSW (likely) :active, 2026-09-22, 2027-01-15
section Business Units
CE Shopware :2026-09-22, 2026-10-15
ECMD Shopware :2026-09-22, 2027-02-01
Gemaire Shopware :2026-09-22, 2026-11-15
Baker Shopware :2026-09-22, 2027-01-31