Shopware Migration Program Analysis — Week Ending 2026-07-28

Executive Summary

  • SXSW platform crawls to 64%: Only +7 completions (596/927) with +18 scope growth this week — velocity collapses to 1 story/day from prior 2.6, now tracking 6 weeks behind original projections
  • Review pipeline clearing: Stale tickets drop dramatically from 13 to 2 (85% reduction) with max age falling from 106 to 71 days — first major breakthrough in chronic review backlog since May
  • ARROW UI launches: New board (ARROWUI) appears fully formed at 13/50 (26%) completed — unclear if net-new work or reclassification, requires investigation into origin and velocity baseline
  • Data migration stuck at 2.4%: Only 1 of 42 BU×category cells Done (Peirce Customers), 18 cells still "NYS" — zero progress for 21 consecutive days with production deadline invisible
  • Commit velocity drops 40%: 365 commits this week (down from 572) despite 24 active contributors — Baker/ECMD show continued inverse pattern (board growth, minimal commits), CESW flatlines completely

Progress Overview

SXSW  [████████████████░░░░░░░░] 64% (596/927)
CESW  [███████████████░░░░░░░░░] 67% (454/674)
W1DA  [██████████████░░░░░░░░░░] 65% (127/195)
ARROW [███████████████████░░░░░] 81% (51/63)
ARUI  [██████░░░░░░░░░░░░░░░░░░] 26% (13/50)
FRONT [█████████████████████░░░] 89% (462/521)
INFRA [█████████████████░░░░░░░] 85% (90/106)
ECMDS [██░░░░░░░░░░░░░░░░░░░░░░] 10% (35/349)
GSHOP [░░░░░░░░░░░░░░░░░░░░░░░░]  0% (0/31)
BSWM  [███░░░░░░░░░░░░░░░░░░░░░] 14% (34/239)

1. Shopware Platform - SXSW Initiatives

Current State: 596/927 stories complete (64%), +7 done / +18 scope since July 22

Week-over-Week: Velocity plummets to 1 story/day (7 in 7 days) from prior 2.6, slowest burn rate in 8 weeks. Scope inflation continues at +18 net, suggesting discovery is outpacing execution. Initiative breakdown shows mixed signals: Infrastructure (44% → remains stuck), Auth (97% stories), Catalog (70%), Cart/Checkout (61%), but 9 of 11 initiatives still in "blue" status.

Repository Activity: Only 44 commits to peirce-shopware (down from ~60+ in prior weeks), distributed across Adrian (11), Rob (9), Paul (4), Josh (2), Htun (5). Minimal coordination across initiatives — no visible orchestration of the platform layer.

Risks:

  • Velocity collapse from 7.3 → 2.6 → 1.0 stories/day over 3 weeks suggests either resource reallocation or systemic blockers
  • Scope growth (+18 net) outpacing completions (+7) means target date slipping at ~1.6 weeks per calendar week
  • Infrastructure initiative stuck at 44% for multiple weeks — foundational blocker to downstream work

Pipeline: 39 stories in Open, 243 in Discovery, 38 Dev Complete, 16 Active Dev — healthy funnel but poor conversion rate


3. Arrow - Domain API / Graph

Current State: 51/63 complete (81%), no movement since July 22

Stasis: Board frozen for third consecutive week. Repository shows only 97 commits this week (down from ~150 in prior weeks), primarily Mitchell (17), rdumitru (21), Robert (10), Joshua (5). Work appears concentrated on SupplySync unification and Baker/ECMD scope alignment rather than story completion.

Context: DOMAIN-376 (ErpAccount collision fix) and DOMAIN-410 (SupplySync merge) PRs merged this week suggest backend refactoring work not reflected in board movement. Gap between repository activity and Jira tracking indicates either incomplete story decomposition or execution happening outside the board.


4. Arrow - Frontend / Open Components

Current State: 462/521 complete (89%), +19 done / -7 scope since July 22

Positive Signal: Rare scope reduction (-7) alongside solid completions (+19) suggests cleanup and convergence. Repository shows 233 commits from Gabriel, 95 from Lino, 65 from German — sustained velocity across checkout, shopping lists, branch filters.

Notable Work: ARROWUI-114 (setDataOnCart unification), ARROW-2633 (shipping methods), ARROW-2642 (checkout order data) all landed. Review pipeline shows 1 Ready for Review, 3 In Review, 1 Testing — healthy flow.

Risk: Scope reduction may indicate deferred work moving to ARROWUI board (see Section 11 below).


5. Arrow - Infrastructure / Cross-cutting

Current State: 90/106 complete (85%), no movement since July 22

Stasis: Frozen for third week. Only 9 commits to infrastructure-related repos. "Homans to ARROW + Shopware" epic shows 10/13 complete but stuck — likely blocked on SXSW-487/485/488 CI/CD issues noted in environment tables.


11. Arrow UI (ARROWUI)

Current State: 13/50 stories complete (26%), new board appeared fully-formed this week

Analysis: Board materialized with no prior history. Current velocity: 13 completions in first recorded week, suggesting either rapid delivery or reclassification from ARROW board. Repository activity shows work on Homans customization (Pablo: 80 commits, Gabriel: 55), branch filters (Lino), checkout updates (Gabriel).

Uncertainty: Unclear if this represents net-new scope or migration from ARROW Frontend board (note the -7 scope reduction there). Needs clarification on:

  • Origin of the 50 stories (new vs reclassified)
  • Why split into separate board now
  • How to baseline velocity for projections

Pipeline: 7 epics listed, mix of Homans-specific work (Warranty, Wingman), E2E testing, and bug fixes. All epics show "light" status except "Homans to ARROW + Shopware" (blue, 10/13) and "Frontend Bug Fixes" (blue, 3/8).


6. CE Shopware (CESW)

Current State: 454/674 complete (67%), completely flat since July 22 (+0 done, +0 scope)

Stasis: After weeks of violent board churn (+80, +46 completions), CESW flatlines. Repository shows 73 commits from Emil (system builder, similar products, login-as-customer), 59 from Blake (DMI subgraph, docebo integration, punchout), 31 from Scott (punchout, order approval). Real work visible but not closing Jira stories.

Discrepancy: 163 commits of production code merged but zero story movement suggests:

  • Work happening outside sprint boundaries (tech debt, refactoring)
  • Stories too large to close within week
  • Tracking discipline breakdown

Pipeline: 148 Open, 30 Under Code Review, 14 Blocked, 19 Deploying — review pipeline healthy but Open backlog growing. Emil's 23 Jira tickets this week all related to customer import, mobile integration, lists — substantive features not yet reflected in board.


7. Domain API (W1DA)

Current State: 127/195 complete (65%), no movement since July 22

Stasis: Frozen for 8th consecutive day. Repository shows only 17 commits (Mitchell: 17), all related to SupplySync merge and Baker scope alignment. No story closures despite active repository work.

Context: Prior analysis noted "Field-reconciliation pass against Conduit" (CESW-1080) and customer-api subgraph work — appears to be in execution but not landing as story completions.


8. ECMD Shopware (ECMDSW)

Current State: 35/349 complete (10%), no movement since July 22

Scope Explosion: Board grew from 64 → 323 → 349 stories over 3 weeks, now 10× the original size. Only 20 commits this week (Lucian: 20) focused on environment setup and customer contract work. Board composition: 290 Backlog, 16 Ready for Dev, 1 Active Dev, 1 Blocked — suggests massive story decomposition event happened but execution hasn't started.

Projection: At zero velocity and 314 stories remaining, board is effectively indefinite. Needs immediate re-scoping or resource injection.


9. Gemaire Shopware (GSHOP)

Current State: 0/31 complete (0%), no movement since July 16

Frozen: 12 days with zero progress. Only 5 commits this week (Damian: 5) on Scene7 viewer component. Board shows 66 "IN QUEUE", 6 "BLOCKED", 6 "In Progress" — but no tickets moving to Done.

Blockers: GSHOP-100 (Customer Cards Data) blocking GSHOP-96 for 19 days, GSHOP-108 (Arrow Graph BOM) blocking GSHOP-86 for 5 days. Both require Mike D'Ottavio (non-contributor this week) and Nikolay Prudnikov (3 commits).


10. Baker Shopware (BSWM)

Current State: 34/239 complete (14%), no movement since July 22

Inverse Pattern Continues: Board grew from 32 → 234 → 239 over 3 weeks but only 67 commits this week (Tyler: 67, all frontend customization work). Gap between board size and commit volume indicates either aggressive story breakdown without corresponding execution, or work happening in parallel repos not counted.

Repository: Only 5 commits to baker-shopware (Cleo: 5), all quote plugin updates. Real frontend work in baker-headless (67 commits) but disconnected from Shopware board tracking.


Review Pipeline Aging

Breakthrough: Stale ticket count drops from 13 to 2 (85% reduction), with max age falling from 106 to 71 days. Major tickets closed this week:

  • SXSW-567, -573 (Delivery resolvers) — 20-25 days
  • SXSW-1129, -1137 (Customer export) — 20 days each
  • 10+ other 15-20 day tickets

Remaining Stale:

  • SXSW-651 (Cross-BU Feature Analysis - Warranty Parts List) — 71 days in review, Cleo Hister
  • SXSW-915 (Customer Export CLI anonymize flag) — 60 days Dev Complete, Joshua LaRose

Current Pipeline: 70 items total — 33 Dev Complete (median 20 days), 12 In Review (median 4 days), 24 Under Code Review (median 5 days). Pipeline much healthier than 2 weeks ago, but two chronic cases need escalation.


Repository Activity & Team Velocity

Overall: 365 commits this week (down 36% from 572 last week) from 24 contributors across 18 repos. Velocity drop coincides with SXSW story completion slowdown, suggesting resource constraints or coordination issues.

Top Contributors:

  • Gabriel Guzmán: 233 commits (checkout, shopping lists, branch filters) — Watsco Platform team, frontend-focused
  • Lino Rallo: 95 commits (branch filters, typeahead, PLP improvements) — Watsco Platform, frontend
  • Pablo Romero/David: 80+55 commits (brand pages, feature flags, address forms) — split identity issue
  • Tyler Hawkins: 67 commits (Baker cart customization, hooks) — Baker team

Team Distribution:

  • Watsco Platform: 7 contributors, ~500 commits (Gabriel, Lino, Pablo, German, Mitchell, Robert, Tiberio)
  • CE: 4 contributors, ~186 commits (Emil, Blake, Scott, Mikalai) — real work but no board movement
  • Human Element: 5 contributors, ~65 commits (Adrian, Cristian, Ilir, Rob, Joshua) — scattered across SXSW initiatives
  • ECMD: 1 contributor, 20 commits (Lucian) — not enough for 349-story board
  • Gemaire: 2 contributors, 8 commits (Nikolay, Damian) — not enough for 31-story board with 6 blockers
  • Baker: 3 contributors, 76 commits (Tyler, Cleo, Nick) — frontend work disconnected from Shopware board

Inverse Patterns Persist:

  • ECMD: 349 stories, 20 commits — 17.5 stories per commit (impossible ratio)
  • Baker: 239 stories, 76 commits — 3.1 stories per commit (still inverted)
  • Gemaire: 31 stories, 8 commits, 0 completions — execution problem

Repository Hotspots:

  • ecommerce-supergraph: 163 commits (primary integration point)
  • watsco-frontend-boilerplate: 145 commits (template improvements flowing to BUs)
  • peirce-frontend: 142 commits (80% sync from boilerplate)
  • cesw: 57 commits (despite zero board movement)

Active Branches: Repository shows 12 long-lived feature branches (>7 days old), suggesting parallel workstreams not yet merged. Notably:

  • feature/<a href="https://watsco.atlassian.net/browse/SXSW-1088" target="_blank">SXSW-1088</a>/login-as-customer-exchange (Adrian) — 4 days
  • feature/<a href="https://watsco.atlassian.net/browse/CESW-888" target="_blank">CESW-888</a>-Proxy-Login (Emil) — active
  • feature/<a href="https://watsco.atlassian.net/browse/ARROW-2633" target="_blank">ARROW-2633</a>-Fulfillment-And-Shipping-Methods (Gabriel) — merged after 8 days

mermaid
gantt
    title Projected Completion (based on current velocity)
    dateFormat YYYY-MM-DD
    todayMarker stroke-width:2px,stroke:#ef4444
    
    section Core Platform
    SXSW (likely)            :active, 2026-07-28, 2027-03-15
    SXSW (optimistic)        :crit, 2026-07-28, 2026-12-15
    
    section Business Units — Realistic
    CE Shopware (stalled)    :2026-07-28, 2027-06-15
    Baker (indefinite)       :2026-07-28, 2028-01-15
    ECMD (indefinite)        :2026-07-28, 2028-06-15
    Gemaire (blocked)        :2026-07-28, 2027-09-15
    
    section Infrastructure
    Arrow Graph (frozen)     :2026-07-28, 2027-01-15
    Arrow Frontend (near)    :2026-07-28, 2026-09-15
    Arrow Infra (frozen)     :2026-07-28, 2026-12-15

Velocity-Based Projections:

  • SXSW: At 1 story/day, 331 remaining = 331 days (March 2027). Even at prior 2.6/day = 127 days (December 2026). Original projections called for August 2026.
  • CESW: At 0 stories/week (frozen), completion date is undefined. Prior 6.6 stories/week would yield 33 weeks (March 2027).
  • ECMD: At 0 velocity with 314 remaining, indefinite. Even at hypothetical 5/week = 63 weeks (October 2027).
  • Baker: At 0 velocity with 205 remaining, indefinite. Even at 6/week = 34 weeks (March 2027).
  • Gemaire: At 0 velocity with 31 remaining and active blockers, likely 16+ weeks (December 2026) if blockers clear.

All BU boards are tracking 6-12 months behind any reasonable production target. SXSW platform tracking 4-8 months behind original schedule depending on velocity assumption.