- Major platform sprint landed: SXSW jumped +85 stories week-over-week (377/846, 45%) after clearing the review backlog—exactly as predicted. Velocity is strong. The apparent +134 scope growth is a tracking maturity improvement, not requirements churn (see below).
- BU boards show real activity: CESW +2, W1DA +3, ECMDSW +4 stories completed with healthy in-progress pipelines (39, 20, 11 respectively). Tracking visibility problem solved.
- Arrow core streams still frozen: Graph (51/63) and Frontend (376/426) show zero ticket movement for fourth week despite active repository commits—work is happening on BU boards instead.
- Staging restart planned: BU Shopware environments intentionally paused — targeting mid-July for staging, mid-August for production. Not a blocker.
- Infrastructure closes gap: +2 stories (80/101, 79%) with active Homans migration work (1/8) finally starting.
1. Shopware Platform - SXSW Initiatives
Current State: 377/846 stories complete (45%)
Week-over-Week: +85 stories completed, +134 apparent scope expansion (vs. +17 stories/+4 scope last week)
The massive story completion surge validates last week's prediction—the 81-item review backlog cleared. The +134 scope increase is not requirements churn—it's a tracking maturity improvement. The team promoted subtasks to stories and stories to epics for better visibility:
- 14 new BU environment epics (SXSW-945–979) created for Staging + Production setup across all 7 BUs
- SXSW-902 (Shopware Core Functionality) added with sub-stories
- Together these account for 126 of the 134 "new" stories—118 of which are in Discovery
- The old single BU environment epics (SXSW-430–436) are now marked Done/Rejected, replaced by this granular structure
Real velocity: +85 stories completed against existing work. The "scope expansion" represents previously-invisible work (subtasks) being formalized into trackable stories. This is a positive signal—the team is maturing their planning, not adding scope.
Pipeline Analysis:
- 61 items now in review (down from 81)
- 15 in active development (up from 14)
- 299 still in Discovery (up from 228—mostly the 118 new env stories)
- 7 blocked (down from 10)
By Initiative (only showing movement):
- Infrastructure: 98/226 stories (43%, was 48%)—regressed due to scope increase
- Cart & Checkout: 41/136 (30%, unchanged)—critical path still lagging
Action Required: None on scope—this is healthy planning maturation. Continue tracking the 118 Discovery stories to ensure they get sized and prioritized before the cutover window.
2. BU Boards - Confirmed Activity
CE Shopware (CESW): 216→218/348→356 (+2 stories, +8 scope)
- 39 items in progress (unchanged)
- 132→140 open items
- Repository shows 30 commits from 3 authors (Scott Kovach, Emil Stewart, Blake Saunders)
- Active work on Registration/Leads (CESW-246), Inventory (CESW-393), Auth0 integration
Domain API (W1DA): 99→102/205→245 (+3 stories, +40 scope)
- 20 items in progress (unchanged)
- Massive 40-story scope increase suggests Domain API requirements expanding
- Active: Shopware Module Split (9/12), Distance Units (DOMAIN-261, 3/15)
ECMD Shopware (ECMDSW): 12→16/24→32 (+4 stories, +8 scope)
- 11 items in progress
- Highest completion rate: 50%→50% maintained despite scope growth
- Infrastructure (9/17), Catalog (4/7) progressing
Analysis: The BU boards show healthy velocity with work actually landing. The 48-story combined scope increase across these three boards partially explains the SXSW scope growth—BU-specific requirements are being discovered and formalized.
3. Arrow - Domain API / Graph
Current State: 51/63 stories complete (81%)
Week-over-Week: Zero movement for fourth consecutive week
Repository Status: No commit data (clone timeout)—but last week showed 100 commits from 8 authors
Reality Check: The team is actively migrating Domain API work from the ARROW project to the W1DA (DOMAIN) project. This is an intentional consolidation — Arrow Graph will wind down as remaining epics are moved to W1DA for unified tracking.
Recommendation: Continue migration. Once complete, the Arrow Graph section can be archived and W1DA becomes the single source of truth for Domain API progress.
4. Arrow - Frontend / Open Components
Current State: 376/426 stories complete (88%)
Week-over-Week: Zero ticket movement for fourth consecutive week
Key Win: Successful full-stack demo last week — Arrow Frontend → Domain API → Shopware end-to-end connectivity confirmed. Did not get through checkout, so happy path is not yet complete.
Repository Activity: 7 commits from 4 authors (Mitchell Cowie, Pablo Romero, Gabriel Guzmán)
- Launch configuration work
- Ordin Ansible scripts (ARROW-2462)
- Token management fixes (ARROW-2463)
Commit velocity down (41 last week → 7 this week)—team shifting from feature work to deployment/infrastructure.
Remaining 50 Stories: Customer-facing features (Order Approvals, AHRI PDP, Compare, Quick Order, Part Finder) plus checkout completion. Given the successful demo, these are real remaining work items, not orphans.
Next milestone: Complete checkout flow to achieve happy path end-to-end. Also actively working on a secondary skin (Homans + Peirce) to validate the multi-BU theming approach.
5. Arrow - Infrastructure / Cross-cutting
Current State: 80/101 stories complete (79%)
Week-over-Week: +2 stories completed (first movement in weeks)
Key Progress:
- Demo Environment Bugs: 23/28 (82%)
- Homans to Arrow migration: 1/8 started—finally breaking ground on this epic
- Gemaire Support: 5/6 (83%, was 4/6)
Environment Status: The 6 CI/CD deployment tickets (SXSW-484–489) remain in Blocked status by design — staging restart is planned for mid-July.
6. BU Environment Deployment
Arrow Shopware Environments: Intentionally paused. The team made a deliberate decision to hold staging deployments while the Domain API and frontend stabilize. Plan to restart:
- Mid-July: Staging environments for all BUs
- Mid-August: Production environments
This is sequencing, not a blocker. The tickets (SXSW-484–489) remain in Blocked status as a tracking artifact but are not impeding active development work.
Arrow Magento: Progressing normally through Ordin with Gemaire/CE reaching Staging.
Shopware Core: All BUs paused pending the same mid-July restart for staging environments.
7. BU Frontend Implementation
Peirce Phelps: 7/8 complete (Account still WIP)—unchanged for 3+ weeks
Gemaire & Carrier Enterprise: All 8 areas in WIP—unchanged
All Others: Not started
Analysis: Frontend work appears stalled across all BUs. The 7 repository commits this week don't align with ticket movement, suggesting either: